Grid View / Repeating Task
Hi,
Is there a way to make a task "re-occuring"?
For example, I have a design meeting that occurs every tuesday and thursday for the next 3 months. Instead of manually typing "designing meeting" and manually selecting tuesday and thursday for each week for the next 3 months, is there a way I can populate this automatically?
Answers
-
In the Grid View in the Date Column of say Row 2 put
= Date@Row1 + 7
Then copy the Design Meeting Row Down and it will automatically add 7 days to Each
When you are done, select all the dates you created and Copy them
Then on the same cells right-click and choose Paste Special as Values to remove the formulas
Might be easier to do all Tuesday meetings than All Thursday meetings trying to figure out how to alternate every other one
Then you can resort the grid back into date order
Brent C. Wilson, P.Eng, PMP, Prince2
Facilityy Professional Services Inc.
http://www.facilityy.com
-
I wrote the formula but it says #UNPARSEABLE.
What am I doing wrong?
-
I even tried this but it didn't work:
Any help would be appreciated!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.8K Get Help
- 406 Global Discussions
- 218 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives