How to preserve Gantt chart dependencies in a report?
Hello,
I have created a report of my PP to display Gantt view of tasks and most importantly the dependencies on a dashboard report.
However, the Gantt view loses all dependencies when you create a report!!
Any solution to this?
Thank you!
Answers
-
Hi Abnoos
Unfortunately, Smartsheet reports are just view of rows and does not retain the parent-child relationship, and thus the dependencies are not shown. It just shows the task level start and finish dates.
Best Regards
Amit Wadhwani, Smartsheet Community Champion
Smartsheet CoE, Ignatiuz, Inc., Exton, PA
Did this answer help you? Show some love by marking this answer as "Insightful 💡" or "Awesome ❤️" and "Vote Up ⬆️"https://www.linkedin.com/in/amitinddr/ -
Boo!
-
Thanks for the post, we have been tearing our hair out trying to work out how to get the dependency lines showing on the report. Good to know we aren't going mad :)
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives