"Record a Date" Workflow not acknowledging Date columns
I have a dependency-enabled sheet with Start Date and End Date columns, both formatted as "Date/Time" column types. I want to create a workflow that will change my End Date to the date "Status" changes to 'Complete'.
The problem is that when I select "Record a Date" in the "Select an Action" section of the Workflow it states that "There are no date columns" when that is certainly not true.
How can I inspire Smartsheet Workflow to recognize my End Date column in the Workflow?
Answers
-
Hi @Chris Albig
I hope you're well and safe!
Unfortunately, it's not possible because they are used for the schedule calculations (Dependencies), but it's an excellent idea!
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 85 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives