Hi all,
Consider this situation:
- report is due 8/1/22
- work is complete on 6/1/22
- report is written - predecessors are #2 and #3FF
If the report takes 2 days to write, those two days will end on 8/1, since there's a FF predecessor relationship - great.
If the report takes 90 days to write, the predecessors are in conflict - can't start writing the report until the work is done, but the report has to be done by the deadline.
In this case, smartsheet silently violates the FF predecessor:
Is there a way to find this conflict? It would be very helpful if conflicting relationships were called out - make the link from "report due" to "write report" and/or make the predecessors column red or something. Silently ignoring the constraint seems problematic.
thanks,
Aaron