In the below schedule of values, the $ value of each child task is the parent value multiplied by a weight. For forecasting purposes, let us assume that 25th of every month, each line item is billed depending on the whether the start and finish dates fall within the period.
In the below example, activity on Row 20, is to happen between 2nd February, till 6th of April. The total value is $23,437.50. Assuming that the billing date is 25th of each month.
For this activity, if we are to forecast and expect to bill as below :
- 25th February, for work done between 2nd February and 25th February.
- 25th March, for work done between 26th February and 25th March.
- 25th April, for work done between 26th March and 6th April .
And the total of the above three billings will be equal to $23,437.50.
Question :
- What formula is to be used in the column February 2023, March 2023, April 2023 for the Row 20 ?
- Let us say, there is another column called May 2023, what formula to use so that for Row 20, the value returned is $0 ?
- Is it possible combine 1 & 2 ?
The whole idea is able to generate a financial forecast tied with the schedule. As the dates or values are changed, the columns such as February 2023, March 2023, April 2023 should automatically update based on a formula.
Thank you in advance for your help.