Automation keeps sending notifications even if the criteria are no longer met
Michaela Kamenska
✭✭✭✭✭✭
Hi all,
I was wondering if someone can advise. Basically, I've set up automation to notify team members if certain tasks are not completed and date is in the past. This is the below set-up.
I've tried "100%" in the last condition instead of just "100" but the notifications keep coming regardless. Can anyone advise where I'm making a mistake? As you can see in the below snapshot, the task is marked as 100% but the notifications keep coming:
I've got standard dependency settings too:
Tags:
Answers
-
Try setting that last condition to be where % Complete is less than 1.
Smartsheet reads percentages as a part of a whole, so 100% = 1, 50% = 0.50, so on and so forth.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 450 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives