Out of Practice, Need 2 Variable Flag (At Risk) Help

KristiTRUSD
✭✭✭✭
I haven't been a good girl practicing my formulas. Everything I've tried is coming up Uparseable.
What I'd like to do: Red Flag when "Expected Completion Date" is within 5, days, or in the past, and "Current Status" does NOT equal "Complete".
I'm feeling pretty silly that I've spent so much time trying to get this to work. I'd love any help offered on a working formula
Tags:
Answers
-
Try something like this:
=IF(AND([Current Status]@row <> "Complete", [Expected Completion Date]@row <= TODAY(5)), 1)
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.7K Get Help
- 472 Global Discussions
- 200 Use Cases
- 514 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 82 Community Job Board
- 520 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!