How to create a chart that display Health of tasks in a project?

jehup
✭✭
I am having issues to plot the "Health" of tasks in a project. Below is a screen shot of what I want to display in a Pie or bar format. Thanks
Answers
-
two options....
- create a metrics sheet - In Primary Column enter R,G&B
- in the 2nd colum. =COUNTIF({source sheet - health},health@row) and drag this down
- run your graph off the metric sheet
Option 2...
- create a report. Two columns only - Primary & Health
- Group by health
- Summarize by health - count
- run your graph off this report.