How to create a chart that display Health of tasks in a project?
jehup
✭✭
I am having issues to plot the "Health" of tasks in a project. Below is a screen shot of what I want to display in a Pie or bar format. Thanks
Answers
-
two options....
- create a metrics sheet - In Primary Column enter R,G&B
- in the 2nd colum. =COUNTIF({source sheet - health},health@row) and drag this down
- run your graph off the metric sheet
Option 2...
- create a report. Two columns only - Primary & Health
- Group by health
- Summarize by health - count
- run your graph off this report.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 213 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives