Percent Complete Plan Formula

Options

Smartsheet Community:

I am Tracking Plan VS Actual and have a % Complete Formula to Track The Plan. However, My Formula is at 100% Complete for Plan, but the due date is 11/28/22. Therefore, it should be Calculating 100% Complete as of Today. Does anyone have any idea where in my formula is incorrect?

% Complete (Plan): =IF(IFERROR(IF(AND(TODAY() >= [Start Date (Actual)]@row, TODAY() <= [Finish Date (Actual)]@row), ROUND(NETWORKDAYS([Start Date (Actual)]@row, TODAY()) / [Duration (Actual)]@row, 2), IF(TODAY() > [Finish Date (Actual)]@row, 1, 0)), 0) > 1, 1, IFERROR(IF(AND(TODAY() >= [Start Date (Actual)]@row, TODAY() <= [Finish Date (Actual)]@row), ROUND(NETWORKDAYS([Start Date (Actual)]@row, TODAY()) / [Duration (Actual)]@row, 2), IF(TODAY() > [Finish Date (Actual)]@row, 1, 0)), 0))

Thanks

Tags:

Answers