How to show budget only for one out of several years budget plan?
Hi dear community, i build up a project plan, and its associated budget, wich is running over several years.
Now, I would need to show the total budget per year (e.g. 2023) and i was using the following filter in my report.
The problem i have is that some Work Packages are running over 2 or years and i'm not 100% sure how such WP budget will be calculated.
Any suggestion, help?
Thanks a lot in advance,
Davide
Best Answer
-
Hi all, this is solved now.
Thanks anyway.
Answers
-
Hi @Davide M.
I hope you're well and safe!
Not sure I follow.
Can you describe your process in more detail and maybe share some screenshots? (Delete/replace any confidential/sensitive information before sharing)
I hope that helps!
Be safe, and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi @Andrée Starå , thanks for your reply.
Basically i have different tasks in the same project and their associated cost. See below just for example.
I want to get a report telling me what is the costs of the project for the period 1/Jan/23 to 31/12/23, and i want the program to consider the pro-rata budget if a task is spread over different years.
Thanks in advance,
Davide
-
I found a way in excel how to do this (attached).
I'm still wondering how to do the same in Smartsheet.
Thanks to all.
D@vide
-
Hi all,
I made a lot of step forward but i'm still stuck in finding the final solution. I used the following formulas:
Budget 2022: =IF([Start Date]@row < DATE(2022, 12, 31), NETWORKDAYS([Start Date]@row, DATE(2022, 12, 31)) / Duration@row) * [Total Budget - Pacira]@row
Budget 2023: =IF([Start Date]@row < DATE(2023, 12, 31), NETWORKDAYS(DATE(2023, 1, 1), DATE(2023, 12, 31)) / Duration@row) * [Total Budget - Pacira]@row
Budget 2024: =IF([Start Date]@row < DATE(2024, 12, 31), NETWORKDAYS(DATE(2024, 1, 1), DATE(2024, 12, 31)) / Duration@row) * [Total Budget - Pacira]@row
and i ended up to the picture below.
As you can see the sum of the 3 years budget is more than the total cost needed for this task.
I'm really looking forward to your kind advices.
Best,
Davide
-
Hi all, this is solved now.
Thanks anyway.
-
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives