How can I add a new milestone marker for each date column I have and keep a Gantt flow?

adelmans
✭
I have 3 date columns in a row and want to create a Gantt chart that marks each date separately and has some sort of flow. I tried to set up dependencies and to have the duration column be 0 to use a milestone marker but that automatically made the parent task 0 since dependencies are enabled.
Best Answer
-
Gantt charts can only show one set of dates (start and finish/2 date columns). There is no way to get a third date or another set to display.
Answers
-
Gantt charts can only show one set of dates (start and finish/2 date columns). There is no way to get a third date or another set to display.