Formula Help - Predecessors disabled/Duration calculated formula to exclude holidays

Lori Khoury
Lori Khoury ✭✭✭✭✭
edited 12/08/22 in Formulas and Functions

Hello Smartsheet Community

I had to disable predecessors in this project plan. I worked with the ProDesk to come up with a way to have a calculated weighted formula. There is also a formula that calculate the # of days between start date and end date. However, I just realized that this formula does not excludes holidays. Is there anything I can add the first formula below to exclude holidays and only count for working days?


=IFERROR(NETWORKDAYS([Start Date]@row, [End Date]@row), " ")

=IFERROR(IF([Percent Complete Helper]@row = 1, (AVGW(CHILDREN(), CHILDREN(Duration@row))), [Enter % Complete]@row), 0)




Tags:

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!