Cell Link issues? - helpful workaround tool
Comments
-
Hello all. Same issue, and it may be a deal-killer.
I am a national program manager and have taken on one of our organization's largest programs. At the moment, it consists of 15 sub-projects in one of our markets, and the number will grow significantly as we approach our two largest markets. I am attempting to evaluate the tool as a potential MS Project replacement. I have imported 3 relatively small projects. I have created a single test roll-up project and am trying to create links to the subs. This will allow me to provide senior leadership with a simple holistic view of what is happening with the program.
I am seeing the same issue. Scanning the forums, this issue appears to have been around for years without resolution. If the creation of a link to another smartsheet brings back blank results, I don't know how the tool is usable - I feel like I must be missing something. I have high hopes for SmartSheets and would really appreciate some assistance.
-
I am more than happy to connect Pete and have a look at your set up, just to see if there is something we can do to get those links working as expected.
My email is in my profile.
Kind regards
Debbie
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.7K Get Help
- 425 Global Discussions
- 146 Industry Talk
- 484 Announcements
- 5.1K Ideas & Feature Requests
- 86 Brandfolder
- 152 Just for fun
- 73 Community Job Board
- 494 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 306 Events
- 37 Webinars
- 7.3K Forum Archives