I want changes to the start/end dates in Smartsheet to update/sync in Resource Mgmt
Sign in to see the current vote count, add your own vote, or leave a comment.
Hi @Becky M.
Can you clarify your specific scenario and when your dates are not updating?
Currently, if you have linked the project plan in Smartsheet with Resource Management, then task changes (such as start/end date changes) can flow between the two products. In Smartsheet, you will need to use the Resource Management Panel and click "Update" to push your changes to Resource Management.
Cheers,
Genevieve
The start and end dates of the project do not update as shown below. Perhaps I am misunderstanding what the dates below the project name represent, but it seems like it should be the start/finish dates of the whole project.
In the Resource Management Plan Settings in Control Center, there is no way to link the Client and Project Code fields even though they are not Custom fields and part of the first 3 fields you enter when creating a new project. I can't select them in the Custom Resource Management Information Fields because they are not…
I’d like to see user analytics for WorkApps. I’ve checked the user report available in the Collaborator Pack, but it only shows how many times someone has clicked into the WorkApp each month. I’d like to know: Which resources (dashboards, sheets, forms, etc.) are getting the most traffic? Where are people spending their…