How can I allocate the resources in single task when I have multiple task owners or multiple Task managers?
Best Regards
Saqib
Hi Saqib,
To use Resource Allocation for multiple people for one task you'd need to have the task on multiple rows.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
We need this functionality - I have tasks in my plan that involve more than one resource, for instance, a meeting. If I have a kickoff meeting, I want to show who has to take time to attend that meeting. My plan is already 900+ lines, I would be challenged to repeat a task 5-6 times just to account for the time everyone takes to do that task.
I would like Smartsheet to adjust duration (not work) when I add a second or third resource to the one task. This would save so much time.
I understand if I add more than one resource to a task, it negates tracking time at all.
Thank you
I agree with Mary, this would be a valuable feature and something that most other scheduling tools offer (e.g. MS Project). It would be necessary however to allow for the effort (i.e. hours) of each stakeholder to be adjustable. The sum total could then be shown in the main schedule view.
Hi all, I want to utilize the Smartsheet Dynamic View. Considering the "editor access" type in smart sheet I wonder if the users are aimed to edit the view, should have the editor role? If I am not shared the file with them, will they stay as a Smartsheet user with viewer settings but are able to view the file? Thank you!
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…
I shared access to a user to a specific folder under workspace A (folder is 2025-09-Service Factory). However, I can see that he's shown to have access to all the other child folders under 02-ACTIVE Initiatives. Why is that when I only shared out one folder? Is there a way to only share access to users to ONLY specific…