Sign in to join the conversation:
I want to populate the % Percent field with 100 when the Actual End Date is entered. I tried this formula but I get an error.
=IF([Actual End Date]@row > "0", "100", "0")
Any suggestions?
Hi Dee,
Try this.
=IF(NOT(ISBLANK([Actual End Date]@row)), 1)
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
To add because I can't edit: Have a fantastic week!
Thank you and it works when I turn off % Complete in Project Settings. But then it wont calculate overall project % complete. I am stuck.
Happy to help!
Unfortunately, you can't have both.
You'd have to disable the automatic % Complete feature and add manual formulas instead.
Would that work?
Another option could be a third-party integration like Zapier or the Smartsheet API. Is that an option?
I am getting blocked with edits again as well... -_-
Yes, i get sometimes now as well.
It's back!
HAHAHAHAHAHAHAHAHA!!!!!!!!!!!
Hello I am looking to create a Smartsheet formula that returns the following result: Column A "Created Date" - this column type is a Created date and show results with date and time Column B "Received Date" - this column would round up the "Created Date" and just show date, no time. If the "Created Date" was after 2:00pm…
Trying to create automatic sequential ID numbers based on the date to ship and where the sample goes. Have a general auto numbering Row ID, have (thanks to reading other questions and responses) figured out how to designate a year. Now I would like to number the Internal (INT) shipments separately from the external…
I have a sheet that has data displayed both horizontal and vertical. The primary data is horizontal (date) with information below each date, 4 rows of data. After the data the dates for the next set of data is horizontal with information below it vertical. 1/5/26 1/12/26 1/19/26 1/26/26 JP OS TT LL OS RT RR SS That data…