Start No Earlier Than
Options
Looking for a way to add a "Start No Earlier Than" clause into a sheet? We want to link Task B to its predecessor, Task A, but also indicate that Task B must start no earlier than a certain date. This way if we modify dates/durations for Task A, it modifies Task B while still noting the earliest start date. Any help?
Tags:
Comments
-
Hi Kelci,
Task B needs a second predecessor, call it Task C. Make Task C a milestone on the "Start No Later Than" date.