How do I create an 'At Risk' report, from a sheet, to include on my dashboard?
Do you know what your parameters for "at risk" would be? Also what fields you'd like to report on?
Also, screenshots of your sheet can be helpful if you're willing/able to share, but if you'd prefer they remain anonymous then can you explain what you're trying to report on specifically, like a list of column names and data parameters?
Hi Amanda, are you already doing something on your main sheet to flag at-risk rows? From data on your main sheet, you can create a report which shows only those rows that are at risk. Then you can add that report to your dashboard. These links should give you some inspiration!
Nice one Mike, can I also add that by adding a Report as a tile on your dashboard with the right filter criteria, means you always see the latest "Risk Report" and then add to that, if the visible subject field also hyperlinks to sheet where that Risk exists, you have a high level view that is easily drilled down to the action.
Hope that helps
Richardr
Smarter Business processes.com
Thanks, Richard. Amanda, let us know if you need any help with any of these processes.
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…