I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
I have had approval workflows and notifications built into a couple sheets for about a year now. In the past month, I am getting a lot of feedback saying people did not receive the email request for approval or notification email. It isn't all the time, just sometimes and there does not seem to be a pattern on which ones…