In construction scheduling, we often have weather delays, lag when subs are working out of town, etc in which we need to create a delay mid-task.  i.e., contractor A starts a task on 1/2, is delayed until 1/9 due to cold weather than picks back up and completes the task 7 days later than originally anticipated.  Is there a workaround to build this in to my Gantt?

Comments

I would think this is where you could use Predecessors that would allow you to build-in lag time.

You cannot split a task in Smartsheet like you can in other PMS's.

The only way would be to break the task into two separate tasks (Part a, Part b) link with a dependency and add a lag.