creating mid-task lag?
In construction scheduling, we often have weather delays, lag when subs are working out of town, etc in which we need to create a delay mid-task. i.e., contractor A starts a task on 1/2, is delayed until 1/9 due to cold weather than picks back up and completes the task 7 days later than originally anticipated. Is there a workaround to build this in to my Gantt?
Answers
-
I would think this is where you could use Predecessors that would allow you to build-in lag time.
-
You cannot split a task in Smartsheet like you can in other PMS's.
The only way would be to break the task into two separate tasks (Part a, Part b) link with a dependency and add a lag.
-
Hi,
I am hoping to be able to split tasks with a lag in the middle while the task is on hold - just like the question above by House Plant. Does anyone know if Smartsheet made any updates since 2018 that will allow a task to be split in two without adding another row with the remainder of the task?
Thanks
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives