Keeping track of old baselines
Hi
I want to know if there is a simple way of keeping a log of baselines, e.g. each time it is reset, the old baseline is logged, similar to version control. The idea is that at the end of a project (which underwent change control resulting in the timeline needing to be re-baselined) we will be able to review the changes in the baselines (how many extra days it took and at which points). In other software, new columns appear for Baselines 1,2 3 etc. Is it possible to do a similar thing in Smartsheet?
Thank you, Jen
Best Answer
-
Hi @J.SB
What I would personally do is copy the content of the 3 baseline columns into three new, static columns (text only, no formulas). Then you can reset your Baseline to see live data with your new dates, starting from 0 again.
You can always check the cell history of an individual baseline cell (by right clicking on it) if you want to see historical data.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @J.SB
What I would personally do is copy the content of the 3 baseline columns into three new, static columns (text only, no formulas). Then you can reset your Baseline to see live data with your new dates, starting from 0 again.
You can always check the cell history of an individual baseline cell (by right clicking on it) if you want to see historical data.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
A lovely, simple solution. Thank you Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives