-
Using Control Center to Track Folder Updates?
Hello, I am unsure of the feasibility of this goal but am hoping someone could provide some insight. Within my organization we have the following structure Workspace → Workspace → Folder. Within this folder we have additional folders that are added through an API integration we have setup. I am hoping we would be able to…
-
Gantt Chart Timescale not aligning with projects fiscal year and start/end dates
I have a project sheet with a Gantt chart where the timescale headings are not aligning with my project’s fiscal year and start/end dates. Configuration: - Primary heading: Quarters (displaying as Q4 2026) - Secondary heading: Months (MMM format) - Fiscal year start: February 2 - Week start: Sunday - Project start date:…
-
Links Not Working
Anyone else having issues with links to other Smartsheet sheets not working on and off? This is the second issue I have had this month. My table is not populating with the little arrow for the link showing as red versus blue. Error message says: Error: this link is invalid because the linked cell has been deleted. But, if…
-
Can't see sheets in workspace
A colleague of mine and I are working on a project. We've created workspaces and sub-workspaces for different work areas. She is the workspaces owner. I'm an admin. For some reason, she can't see the sheets in the sub-workspaces. I see the sheets, but she can't see them. Again, she is the owner of the workspace folders.…
-
How to include Gantt chart view in automated email?
Hello! I am building maintenance tracking Smartsheet tool for my organization. I have been able to set up and automate my sheet with all other tracking I'd like (date, duration, impacted area, etc.), but I have not been able to determine how to automate including a Gantt view in my automated email communications.
-
Will Smartsheet roll out an enhancement adding the ability to have more that 20,000 rows per sheet?
We use Smartsheet for several data repositories to feed data into other sheets via formula. We are running into issues because of the row limit in sheets. Will you be adjusting the sheet row limit, if so when?
-
How can I make FS dependencies start on the same date the predecessor ends?
Hi everyone, I’m migrating a schedule from MS Project to Smartsheet and I noticed a difference in how FS (Finish-to-Start) dependencies behave. In MS Project, when a task has an FS predecessor, the successor’s start date is set to the same day the predecessor ends. But in Smartsheet, the successor is pushed to start one…
-
Azure DevOps Dashboard
I’m trying to display my Azure DevOps dashboard within my Smartsheet dashboard. I attempted to use the Web Content widget by embedding the dashboard URL, but it didn’t work. My goal is to show the status updates and charts from Azure DevOps directly on Smartsheet. I’ve successfully used the Web Content feature before, so…
-
Link existing table
Hi, I have a table which is linked to database and the table would have new row add. I want a table that have the same data and I can insert a new column to calculate the data. I've found some ways: Cell linking, Report, Connect Your First Sheet to a DataTable. If I use Cell linking, I need to maintain it manually. Report,…
-
Form Submission / Vlookup Integration
Is there a mechanism to achieve either of the following scenarios: Individual populates form and choose a serial # from a drop down list. Can the fields on the form then use vlookup to auto populate the equipment's location from a master grid sheet on the form prior to submission? OR Individual populates form and choose a…