Login OK but not able to edit any work
I am able to open smartsheet and my account shows that my license is active but I am not able to edit any of the documents that I created 2 weeks ago. I am new to smartsheet so would appreciate any help anyone can provide. I get the following error: I filled out a support request but no response.
-
Ability to Select Default Opening view
It would be fabulous to have the ability to select a tab or area to open automatically when I open Smartsheet, specifically my favorites tab. This way the projects I am focusing on or touch everyday appear automatically when I open the product. Could be an option in my profile settings? One less click and can keep views…
-
Where to start with Bridge?
Hi folks, I am hoping for a pointer in the right direction. I am new to Bridge and need to build a workflow to a) create a project in Resource Management (RM) when the status on a row in Core changes to "Create" and then a follow on workflow that when any of the fields in Core update, reflect those in RM. The challenge I…
-
Merged: Enhanced Report and Sheet Filters for Dates
This discussion has been merged.
-
Dynamic View Link Access for Non-Smartsheet Users
Hello, If I send a link to my contact list (using an automation workflow) of a dynamic view I created, will the contacts that that currently don't have a Smartsheets license be able to view that link?
-
Timeline View (Reports)
Hi, Is there a plan to provide the option to manually re-order the swim lanes in timeline view? I am using a report that pulls from several sheets and it would be helpful to have this option without creating helper columns in each of the source sheet to do so. Additionally it would be helpful to have the "fields shown"…
-
Lag in Dependencies AND elapsed days in the Duration
There has been a recent change within the last month or so that caused rows that were using lag in the dependency AND elapsed days in the duration column (which is an INCREDIBLY common occurrence in our project plans). This recent change has now messed with all dates both past and future that are either directly or…
-
Timeline Integration from Smart Sheet Report - Bug?
Has anyone had issues using the timeline feature built off from a grouped report? Having issues with viewability and when I edit things look how I would expect but after saving many of the timeline views are blank. GIF attached shows how it is currently functioning and how the view changes when in edit mode vs. not.…
-
Adding in new reports via global update
Hi all, Weird problem I am facing today and wondering if something has changed. I have run global updates in the past to push new reports out to active projects (its very nuanced with having to update the report for each project individually) but anyways… Today I tried to run one and the test example worked fine with…
-
Enhanced Global Update Error
Tried enrolling a blueprint that meets the criteria stated on the FAQ page but getting this error for all projects (which are in their own workspaces) Project folder uniqueness validation: Some of the workspaces your projects are stored in contain other projects. The following workspaces contain multiple project folders:…