-
Report from multiple sheets - but automatically including new sheets
We have three basic templates we may use to create a new WorkSpace. Each new WorkSpace represents a project and will have a sheet called "Transition Tracker". I'd like to run a report of information from each sheet in each WorkSpace (so across sheets), but also have it add new sheets as new Workspaces are created. Is that…
-
Combining Two Formulas in One Cell (NETDAYS and Addition)
Hi everyone, I am looking to combine two formulas in one cell (one to calculate number of days; one to calculate completion date, using calculated days). The information below was provided to me by my supervisor to use, but I have been struggling to come up with a solution. Here is the information: Formula: First Product…
-
How to change status based on start/end dates/if completed was checked or not.
Hi there, I've been reviewing past topics but haven't been able to get those formulas to work. I have a sheet where there are start/end dates, and a completed check box column. I'm having trouble figuring out how to create a formula where if start date is in the past and end date is in the future, having it automatically…
-
I want to do a serial IF this then that formula across more than one column. Please help!
My =IF(Child@row="Name1", "Parent1") and it worked to bring the Parent name into the @row, but I am trying to also add a few other Child/Parent combos into it as well. For example, In the Parent Column, I want to combine =IF(Child@row="Name1", "Parent1"), OR =IF(Child@row="Name2", "Parent2"), OR =IF(Child@row="Name3",…
-
Need to tweak Health Indicator formula based on "status date"
I need to tweak the following formula to use a [Status Date] instead of "Today". We publish status reports each Wednesday as of Friday of the previous week. I have added a Status Date column that I will update each week to reflect the status date. Current formula; =IF([% Complete]@row = 1, "Blue", IF([Planned Duration]@row…
-
Date formula help: return 90 days earlier than start date, on the closest Tuesday
Hello, I'm looking for a formula to pull a date that is 90 days earlier than our start date but on the closest Tuesday. Thank you
-
IF Statement - Checkboxes
Hi there, I currently have this formula (below) for my checkboxes that states if the end date is less than 30 days away and the Status of a project is "In Progress" the checkbox is checked off. Currently, if the End Date field is left blank and the Status is "In Progress" the checkbox is marked off. I want to make it so if…
-
Seven Most Current Entries for each Question for Each Location
Hi, I want to pull the SEVEN MOST CURRENT ENTRIES for each QUESTION for each LOCATION. Here's my Master Smartsheet. This is the formula I started using based on responses in the community: =INDEX({TEST Range 2}, MATCH(MAX(COLLECT({TEST Range 4}, {TEST Range 2}, [Q1]@row)), "Clearfield", {TEST Range 5}, 0)) This formula…
-
How do I find the average approval time?
I have a sheet that our PMs approve invoices and another sheet that copies the rows as soon as they are approved. One column is Date Created (Created Date) and the other is Approved Date (Modified Date). When the row is pulled, it captures the modified date when they approve the row. I need to find the difference between…
-
Force upper case on a column
Hello Everyone, I got a question. Is there any way to force upper case on a text column? I have a column where users enter information using iPads and it will be very helpful if the cells will automatically force to have upper case font in it. Thanks