The option to change parent row calendar colors when dependencies are enabled
I have several tasks in each of my sheets that I want to see in a report for major milestones. I want the different tasks to have different colors. Right now it is possible to change the color of children rows on the Gantt Chart/Calendar view, however when dependencies are enable, it's not possible to change the color of…
-
Changing outlines of Gantt chart bars
Hello, I would like to change the colors of the outlines/lines around the bars for sub-activities in the Gantt chart. I was able to change the fill color but the outlines are still light blue. Is there a way to change the color of the outlines? Thank you very much! Kind regards Ulrich
-
Gantt chart & conditional formatting
Hi! Currently the conditionial format of gantt Chart bars is limited to the format option "entire row". As we use the entire row format for visualize the sheet structure (levels), it would be nice to have also the bar Color depending on a single column. Kind regards Michael
-
What is the best way to consolidate data from multiple sheets?
I have multiple projects running side by side and I need a method to view a high level overview of all my projects with real data and a Gantt chart. I know I can use reports but reports do not support Gantt charts or a calendar. Does anyone have a better solution for how to do this?
-
Help: Change GANTT to Year/Month in Widget
I can change my GANTT chart in the project sheet to Year/Month display. But when I create a report and display the GANTT in a widget in the Sight it will only show the GANTT by Week/Day. I need it to show by Year/Month. Can this be done with the report widget? or is there another way to show the GANTT in the Sight for the…
-
Task Duration - Partial day at beginning of period, not the end
Hi, I notice when you add a half day duration to a task, it places the half day at the end of the period, for example a start date of 13/11/17 (Monday) with a duration of 2.5 days will result in the half day being on the Wednesday. Is it possible to make the half day on the Monday and the full day on the Wednesday? I'm…
-
Setting intermittent dates for a single task
I am just getting started with Smartsheets. So far, I am really liking the ease of set up and functionality. One issue I am struggling with is how to set up intermittent dates for a single task. For example, I have a single task where I want to set a date for every other Friday to meet with the client. I don't want to have…
-
Gantt Chart
Hi everyone, The Smart sheet is very good for short term projects. For a long term project that spans across more than ten years, is there a way to download a entire Gantt chart? Thanks, Liping
-
Gantt Chart Task Percentage Color
How do you change the color of the percentage indicator inside the bar of an individual task? In conditional formatting, you can only change the color of the task bar itself and not the color of the percentage of the task. Thank you.
-
is there a way to make children auto-calculate percent complete based on start/end date and the curr
I'm new to this program but not scheduling in general. Is there a way to get each child beneath a parent to calculate % complete automatically, based on the entered start/finish dates and the current date? I'm building construction schedules, and don't want to have to manually update huge amounts of child rows, especially…