-
Calendar vs Fiscal Year/Quarters settings
Hello, I was wondering if there's a way to update the calendar/gantt settings to use quarters based off of our fiscal year. Is that an option? Example - Q1 would be November-January Thanks, -PJ
-
Printing Gantt Charts
Does anyone know how to stop the previous months that have no data in them from being printed with the Gantt chart as its pushing the chart off an A3 size paper.
-
MS Project 2016
Hi All, I've just updated to MS Project 2016 and am unable to import my programmes into Smartsheet. The tasks import ok, but the duration of every task is at zero days. Urgent advice would be greatly appreciated please. Alan
-
Can you set a task to ignore non-working days?
Can you set a task to run for a fixed number of days - regardless of non-working time? For example - I have a 3 day task which is the time it takes for changes to be applied to a User Account (e.g. the addition of new software, changes to security permissions, etc). This takes 3 days. Weekends and Easter Holidays don't…
-
Staff Holidays
Hi, Does anyone know a way of linking staff holidays with Smartsheet. I know how to set up public holidays but, want to see when individual employees holidays effect resource management? Many thanks Faye
-
Collaboration between two client who both use SmartSheet
Looking for suggestions / best practices to make the most of SmartSheet with an important client who is ALSO a huge SmartSheet user. First step they requested is a simple file repository - will grow from there...
-
Import from MS Project
When you import from MS Project do dependencies import?
-
All videos simple - don't show realty use of training needs
Anyone noticed that all trainging videos are so simple of solutions they really don't help with much beyond the most basic. Like conditional formatting - show me how to deal with wanting multiple columns to change format based on one criteria - not a whole row. How do you do that? How many formats do you really need to…
-
How to start building project roll-up with 110 dropdown names to pick also
Where to start, project roll-up, don't want a done of linked cells if can avoid it. Need it simple for user interface. Today using Excel just type it in, pick the color for the cell. The color means something based on a key. There is high-level corrdination of the overall program, then high-level for a project, then…
-
How do you make a Program roll-up
How do you make a roll-up of multiple indivdual projects. Wtihin each of the project dependencies is turned on.