-
Report does not print Gantt (PDF) for all users
I have a report that shows the Gantt on the screen. Most users can export the report to PDF and the Gantt shows in the PDF. I have one user that cannot get the Gantt to show up in the PDF. In the PDF Setup box, they do not see the "Gantt Date Range" selection. They do have the Gantt view selected. Any idea why this user…
-
Resources and Vacations
Is there a way to easily add Resources (who are not Users within the plan) and add their vacation dates so that when a task is allocated to them in a Gantt sheet these vacation days are taken into account as non-working days? I've tried using the Team Vacation Schedule (as…
-
Taking three customized smartsheets and putting them into a new Project sheet
We have three smartsheets that are all unique, but need to combine them into one Project sheet. They're medium size, so copying and pasting might work, but wouldn't that require all formats to be the same? That would take a fair amount of effort to do. I suppose I could export them all and then manually set them up in the…
-
Printing errors
When printing a sheet with a Gnatt view... the bottom row cuts off then half of the line is shown at the top of the next page. I have adjusted the margins and information included in the header/footers but it still cuts off the bottom row. Any suggestions?
-
Gantt view print/preview to show today's date
Is there/have you ever thought of option to show today's date in the print/preview of the GANTT chart view like you do in the main part of Smartsheet?
-
2 Gantt Items: child rows and working backwards
Hello! I'm working on a sheet where I want to include sub-tasks via child rows, but the sub tasks do not all start at the same time, nor are they dependent on one another (and happen to be date dependent) but I need dependencies enabled for the sheet. I can't seem to figure out how to have these items start on a date other…
-
filling columns -has to be a better way!
I have a schedule with close to 2000 lines. I am adding columns that need calculations in them. It currently takes me close to 15 min to either drag the formula down or copy and paste chunks. When I create the column why not provide me an option to enter the formula then and apply that to every row? Smartsheets has been…
-
Separate effort and schedule for project planning
Hi folks, I am wondering people's experiences creating project plans that include separate estimating and tracking of effort versus schedule. A simple case has a task done full time, with full resourcing, with no delays or wait times. In this case, the Smartsheet "duration" works fine for both effort, duration, and…
-
Row Headers Not Aligned
Been using Smartsheet for about a year now in fully up to date Safari OSX 10.12.4 Suddenly yesterday the row headers do not align with their respective rows. Anyone else had this problem? Thanks in advance. David
-
Create Gantt from End to Start
Hello! As a project manager, I often find myself needing to make timelines starting with my end date. However, I have only been able to make Gantt charts in Smarsheet (with dependencies) that I can change the very first start date and then the durations, but I can't work backwards or change start dates to meet my needs! Is…