-
Row Headers Not Aligned
Been using Smartsheet for about a year now in fully up to date Safari OSX 10.12.4 Suddenly yesterday the row headers do not align with their respective rows. Anyone else had this problem? Thanks in advance. David
-
Create Gantt from End to Start
Hello! As a project manager, I often find myself needing to make timelines starting with my end date. However, I have only been able to make Gantt charts in Smarsheet (with dependencies) that I can change the very first start date and then the durations, but I can't work backwards or change start dates to meet my needs! Is…
-
Changing Fiscal Year Start YEAR in Gantt Settings
It is possible to change the fiscal year to be the previous/current calendar year, vs the default of current/coming calendar year in the Gantt settings? My company uses a delayed April start. Thanks!
-
Publishing Gantt Chart
We have a Gantt Chart, we have many columns for various items and the standard Start/Finish/%Complete....... We don't want to share the sheet with a lot of people they don't need all those extra columns, we really just want to show them the Primary/Task Column and the the Gantt Timeline that is it. Is there a way to…
-
View today, including one day and multi-day items on sheet
We track all our promos on one sheet. Some of them run one day, some of them run for several days, some of them run more or less permanently. I need a view of everything running on a given day. The filters do not appear to permit this. Any ideas? Ideally, would like this to run in calendar and gantt views. Alternately, is…
-
Possible to create Gantt Chart in duration of "hours" for single-day projects?
Hi, I created a project smartsheet with gantt dependencies in duration of "hours" for an important project that lasts one day. I was wondering if there is a way to create a gantt chart that only displays one day but shows durations of "hours" on the x-axis instead? (The current gantt chart I see only displays 30 days…
-
Gnatt Frustration
We need more control over scheduling to make this product useful. I just had an issue where after 200 some activities where entered with dates and it was realized it should be based on a 7 day week not 5 day. Switching to a 7 day changed all the end dates. In my view I should have been given the choice of adjusting the end…
-
Change drip down selection for entire coumn
I have added a column to my sheet that is a drop down list column. I would now like to automatically have these selected as, "Not Started". Is there a way to do this other than going down and automatically updating each cell?
-
Project Timeline - Today Bar
Is there a way to add a vertical bar to a gantt chart to highlight the current date?
-
Reporting in Parent/Child format
Hi folks I have a simple sheet with many columns. It tracks all the projects we have and what stage they are in. The parent child relationship looks like this in the primary column: Project A Initiation Planning Execution Closeout For my report, I'd like to still show that relationship so that the gantt chart can be…