-
What's the best way to show Baseline Schedule when it's not available on the Gantt?
We are using the Baseline "workaround" by creating the Actual Start, Actual Finish and variance column formulas. What method has worked for you to compare the baseline to the actual since it's not supported in Gannt view? *already upvoted this feature!
-
Gantt Chart - Duration changing Start/End dates incorrectly
Hello, I am having an issue when in Gantt chart mode. If I have a start date set, and change the duration to be 2 days, the end date is automatically adjusting to be three days from the start date, even though the duration is still correctly listed at 2. This only occurs over weekends and works properly over weekdays so I…
-
Viewing Gantt Chart History
Does anyone know how to view gantt chart history? Dates that have passed rather than prior versions. Thanks!
-
Reverse Engineering a Timeline
Is there an easy way to reverse a timeline that was originally based off of a start date, but should be based on the end date? We plan a lot of meetings where the meeting dates are always moving and we want to adjust the way we have our timelines so we can change the meeting date and Smartsheet can fill in the dates of the…
-
Schedule Duration Issues
I've been working in a CPM schedule. The original showed a 141 day duration, starting 12/12 and ending 05/04. I'm updating some of the relationships as I had to rearrange the work pattern a bit, now my schedule shows 144 days, starting 12/12 and ending 6/29. Does anyone have an answer as to how I gained only 3 days…
-
Report Builder Gantt Chart is off
I've been playing around with report builder, to create a summary page of all my sheets. I have a check box I use to filter the lines I want on the report, which are typically the first/top line, which is the entire project. The Gantt view in each sheet is correct, but in the report, every line has the gannt shifted by one…
-
numbering child rows
I have a sheet I've been using for a while. I just added a column and set it up to auto number. All the rows increased sequentially, e.g. 1, 2, 3 etc. The child rows, and their child rows continued in orer, in otherwords the child of parent row #1 was #2. I'd like the child of Row #1, to be 1.1 or something like that. Be…
-
Start / finish Dates
I need to show the proposed start/end dates in the program to my client. He also wants to see actual start/finish dates. Is it possible to do this?
-
Percent Complete not adding up
I need some help figuring out how to make my "% Complete" column reflect the actual percentage using my "Hours" column and not "SLA" (days). The sample below is clearly incorrect. It should be more like 64% complete. I'm totally stumped.
-
JIRA Integration: automatically fill in "Start Date" when a Status has been changed?
Hi Smartsheet Community, We've integrated JIRA into Smartsheet. We're looking to automate some more fields. When using the gantt charts, some of the field we are manually filling are and Start Date and End Date. Is it possible to accomplish the following? 1) When a JIRA [Status] has been switched from To-Do --> In Progress…