I'm entering 2 hrs in duration, but over in the gant chartt, it shows 2 days. advice on how to enter/view this corretly?
I've been using smartsheets for projects plans for some weeks now and can manage all of the usual functions that I'm used to but I've got a new challenge. How do i add variable contigency to the duration of a task based on a BRAG status? Example: In an Agile development environment the first pass estimate is RED and should…
I know there is a way to do this but for some reason I am stuck. I have an event taking place on 5/25. So that needs to be the due date and it CAN NOT MOVE. I then have maybe 40 or so tasks leading up to it, all of which have to occur in certain sequences. I am not able to set up the project. One of two problems occurs.…
I have a Team Vacation schedule (the team is working in 4 different countries) and have also added dates for holidays which the company is also off according to the local holidays. Is there a way so that these holidays will show down the Gantt chart so that I don't have to always scroll to where the Holiday is set to see…
I have a need to combine the detail of the start/finish date from the grid view with the visualization of the Gantt chart view. Is this possible?
I apologise if this is a simple question; I am new to using smartsheet. For the Gantt chart attached, I notice that the 2nd row on the Gantt chart has bold text; how do I go about removing this? For context, the Gantt chart refers to a project that consists of 3 mini projects within it (in grey). And the constituents of…
Hi I'm making a sheet on my project started a little before the actual day I created the sheet. I want to plot in some activities which has occurred in the beginning of my project. However the calender provided is only 1 month back. Is it possible to add a month or two back in time?
MS Project has the capability to maintain duration in days or weeks independently of work (hours). Does this capability exist in Smartsheet?
How can I generate the sub dates on a Gantt sheet using the duration? I would like to be able to copy my project and the subdates automatically generate from the head date? This could be generated by the duration. For example If the Head start date is 1/3/2016 I would like the sub dates to auto generate from the duration…
Is there a way to change the font size/etc in the reports and for printing purposes? I have a CAD printer and would love to have the option to print on just one continuous page....and to level all the fonts within the report that i am printing. More options please........