-
Start / finish Dates
I need to show the proposed start/end dates in the program to my client. He also wants to see actual start/finish dates. Is it possible to do this?
-
Percent Complete not adding up
I need some help figuring out how to make my "% Complete" column reflect the actual percentage using my "Hours" column and not "SLA" (days). The sample below is clearly incorrect. It should be more like 64% complete. I'm totally stumped.
-
JIRA Integration: automatically fill in "Start Date" when a Status has been changed?
Hi Smartsheet Community, We've integrated JIRA into Smartsheet. We're looking to automate some more fields. When using the gantt charts, some of the field we are manually filling are and Start Date and End Date. Is it possible to accomplish the following? 1) When a JIRA [Status] has been switched from To-Do --> In Progress…
-
Sheet Name in Task Name
Is there a way to display the Sheet Name in the Task Name or do I have type it in for each task?
-
Misaligned Selected Box in Smartsheet - GUI
Hi, I have noticed the following after using smartsheet on Windows7 and IE 9.0. It looks like the selected box is mis-aligned which is offset from the box that youa re typing in. I have to switch to a new sheet and back again for it to disappear, but it eventually comes back. Any help would be much appreciated. Kind…
-
Time Specific Tasks
Hi I have a project where the time for each task is key during a few days of it. i.e. a task is due to start at 10.00 and continue to 13.00. I may have missed something, but is there a way of creating this rather than just date specific? Thanks Nick
-
Upvote for Gantt Chart by the Hour
Can I upvote for the Gantt to include feature by the hour? We're coordinating with many subs in every 15 throughout the day and we'd like to be able to track delivery activities by the hour (or every 15 min). In the meantime, we'll be using the calendar feature on Outlook to track these activities.
-
Average formula for cell values calculated from another formula
I'm using the SS Jira connector for Jira and have create a template for my team to use. As part of this template I want to calculate the % completed field based on the task's status (the built in % complete of the gantt project only work at the parent level after manually inputing a value for the child task). I've been…
-
Automatically update related tasks when one date changes
Hi! My team is using Smartsheet for project management, and I want to know how to update due dates for tasks that are related. For example, if my original due date is 1/1/17, and there are several other tasks that are related to the starting date (edit, layout, print, etc.), if I change the date of one of those tasks, how…
-
Parent Relation on Progress %
Hi, i am trying to figure out how to create a parent relationship using the progress bar (0%, 25%, 50%, etc...) without having to enter 2 dates. I have a parent with 6 children rows under it. If i choose the progress bar as a colum property from symbols and select progree in the 6 children, I want the average to be…