-
Gantt Chart view for Daily / weekly / monthly Scheduled works
Hi all, We are new to this amazing product. We have separate 9 sites that have numerous different types of scheduled maitenance required at different times. Is there a clear way of displaying this in a gantt chart or spreadsheet type of format? example - Daily clean, weekly service, monthly polish, yearly audit. Thanks in…
-
FF dependecy to push Finish Date, while holding Start Date
Let's say I have two activities, A & B. A has a Start of 3/1/2016 and did indeed start on 3/1. However, it cannot finish until B finishes. So we put down B as a predecessor to A with a FF dependency. The problem I'm seeing is that as B Finish Date gets moved around, the Finish Date for A also moves, which is great; but the…
-
Predecessors without adjusting date?
I've searched the community/help and haven't found a good solution so I'll ask here. There are tasks that have proposed start and finish dates. I have a duplicate task that will show what the actual start and finish dates are because of delays and such. Currently the duplicate has the same start/finish as the original and…
-
The predecessor changes the start and finish dates
Hello, I'm creating a construction schedule. I entered all my start and end dates which automatically calculated the duration. The problem is, when I enter a predecessor, it automatically changes the start and finish dates; why is this happening and what can I do to stop it? Thank you.
-
Bold Milestones in Gantt View
Hello all, Is there any way to make the task name shown next to my milestone in gantt view bold so it stands out from the other tasks?? I have tried every menu and option I can think of with no change in how the task name appears. Thanks!
-
PLANNED VERSUS ACTUAL PROGRESS
hi, is there a way that i can see the planned versus actual progress of the project ? baseline versus actual? thanks.
-
Blank rows showing in printed view
Hi all, I am trying to print out my project plan on an A3 sheet showing my Gantt chart and the tasks. However, when I go to print, I see two blank rows at the bottom of my sheet showing which are not needed and I would ideally prefer for these not to be shown. How could I change my sheet to not show these two blank rows?…
-
Gantt View
Is there a smartsheet timeline for implementing the gantt chart "zoom in" to see hours/minutes of a day? I have been tasked to figure out a 24/7 schedule for 3 crews and would love to see the gantt chart reflect actual change over time....cross over...lag etc.. Also are there any plans to update the printing capabilities…
-
Align Gantt chart with Timeline above?
Hi All: I'm a new user...Ihope this question is not too silly? The horizontal timeline above my Gantt chart is several days off. How do I get it to properly align with the Gantt bars below? My start & finish date columns are correct and the calender view shows the correct dates. Thanks in advance.
-
Counting children in specific column (resolved)
I have a sheet that I'm using to keep track of about 100 projects, eventually each will have several child rows. I'm not using sheet dependencies because I want my parent row to represent how many days are left on the project. To do this I have 6 rows: "Start", "End", "Duration", "Real Start", "Real End" , "Real Duration".…