I'm wondering if I can also use the Gantt chart to identify when we were timely on actions. For example, now it will show a bar correlating with the Start and Finish times. I'm using these as planned start and due dates. If the deliverable was sent after the Finish time, is it possible to have the Gantt chart linked to a…
I am trying to change the Calendar Quarter Headings in Gantt view to reflect our company Fiscal Year Headings. Is this possible? Best, Kat
Hi everyone, I really need help here. My project is of the long sort (several years). I seem to have a problem with far away dates: smartsheet won't 'take' a date in 2018 (I type it or select it in the calender and the box goes blank). My other question is: how do I hides dates (I don't need the next few months on the…
i have add some rows to a certain stage in the construction process, however with each new event i add the start date always goes back to the construction start date no matter if i change it on the calendar function or type the date in please help i am using a gantt chart to plot this project out
Is it true that a % Complete column for a gantt chart can only be updated manually? It would be beautiful if I could use a formula which would update it automatically.
i am trying to build a construction timeline for a project. and i need to use different dependency time frames for different vendors in the same spreadsheet. for example: Permitting works on a business work week schedule. so Mon-Fri no weekends and no holidays. However the GC has agreed he wiil complete his work in exactly…
Is there a way to work on days not normally a workday, ex. work on one saturday. So a 2 day job can be set on friday and saturday, without changing the whole calender of workdays?
Currently I have the ability to manually add holidays to the Gantt view, which default as non-working days. I would like to be able to mark a calendar das a WORKING or NORMAL day, but still have it highlighted (in a color of my choice) on the Gantt view. Ideally, I could even add a description that would show if I move my…
Is it possible to export the whole spreadsheet including the gantt chart into excel? When ive tried to export it to excel previously it only gives me the option to export the actions and not the timeline/gantt chart section. Is this possible?
I want my editors to view the Gantt chart but when they try it says "as an editor or viewer on this sheet, you can not show the Gantt until it has been set up by the sheet owner (Admin). How so I do that so my team can view the calendar or Gantt chart? Thank you,