-
CEO interruptions causes delays
My CEO continually interjects his own agenda into the company's workflow. It's been a challenge for many years, and we all know that he won't change. So knowing that we, as a company, cannot tell him to stop, I would like to create some visual that will show how his interruptions cause delays in deliverables of other…
-
Weeks/Days Remaining Formula
How can I create a column that displays "x Weeks and x Days remaining" until a task's start date? I know about RYG Balls and what I can do with conditional formatting, but those just aren't sufficient for my needs. In Excel/Sheets I use the MOD function to do this using the following formula: =IF(([Start…
-
Conditional Formatting or Formula
Good Day All: I am trying to use Greater Than Conditional Formatting for two columns. However, Conditional Formatting does not allow you to select 2 columns. Perhaps, I have to use a formula? Here is what I would like to do: If % Complete (Planned) is Greater than % Complete (Actual), then Red If % Complete (Planned) is…
-
Date Calculation \ Automated based upon cell value
Good day Everyone: I have a field set up with automated current date, that is used to calcuate\count the # of days of task duration based on current date and task start date. trying to figure out a way to have Actual duration stop counting once the “Sate” of that task.. reflects “Completed”. Or Actual Duration stops…
-
Automate Harvey ball color based on multiple variables
I'm not sure if what I want to do is feasible or not so please let me know if I'm going off the deep end. I would like to have a Harvey ball change color based on several criteria/variables to show likelihood the task will, or won't be, completed on time. Has anyone made a formula that will show a red Harvey ball if the…
-
Multiple reference Formula
Greetings: Trying to create a formula that tracks task duration displayed by "symbol" in conjunction with another condition of the task:... complete, or not started. I was able to get the symbols to show up properly based on calculated duration. However, the bottleneck is related to the formula not picking up a symbol…
-
If and Formula tracking date, progress with ryg status dashboard
To share back with the community here, I'd like to share some key formulas that I've been helped with by the community and extensive testing/fixing. I have a sheet that tracks: * progress for items based on user inputs of %age complete * compared to the progress they should have completed so far (%age expected as of the…
-
Formula errors
* Schedule Variance:* Getting errors Invalid & Unparseable. * My best guess to those results. Are the other columns that it's looking at have cells that are blank. ( actual finish date) resulting from the fact that that task is not completed yet. Thus nothing to draw from * What I’m trying to have the formula pick up...is…
-
Alternative to create a Chart from data on a Report
After reading several discussions I am completely disappointed that I cannot create a Chart directly from a report. So I am looking to understand some alternative options. I have ONE master sheet that tracks ALL of our department project status'. What I needed was to track ONE teams projects - so I created a report so that…
-
Magazine Project Sheet?
My department manages the production of a quarterly magazine and uses SS for the editorial/content management process. Here is the sheet we currently use: https://publish.smartsheet.com/c95e42926fad4be7ae3463eaf2b228da I'm wondering if this seems like the best process, or if there's a simpler solution to a project that…