-
Schedule Duration Issues
I've been working in a CPM schedule. The original showed a 141 day duration, starting 12/12 and ending 05/04. I'm updating some of the relationships as I had to rearrange the work pattern a bit, now my schedule shows 144 days, starting 12/12 and ending 6/29. Does anyone have an answer as to how I gained only 3 days…
-
Personalized user authorization for one cell, and date recording
Hi all, I have a couple questions for all the Smartsheet pros out there! I'm working on a sheet and I would like my team members to be able to update its content. The first problem is that I would like them to be able to edit only some columns and rows, depending on their responsabilities in the project. I mean that each…
-
avoid the shared person delete my row
hi, i see some potential of lose of my data if shared to others. for example, my project schedule shared to partnes and they have to update the status, since they are editor and they can delete my row accidently, how could i avoid from this issue to be repeated?
-
Report Builder Gantt Chart is off
I've been playing around with report builder, to create a summary page of all my sheets. I have a check box I use to filter the lines I want on the report, which are typically the first/top line, which is the entire project. The Gantt view in each sheet is correct, but in the report, every line has the gannt shifted by one…
-
Dynamic Hierarchy
I am in the process of developing some work flow sheets for my team and I would like them to do the bulk of their submissions via web forms. Is there a way to create dynamic hierarchy whereby when a form is submitted, x criteria places that new submission under the correct "Parent"? Let's say that I have 3 Categories…
-
Start / finish Dates
I need to show the proposed start/end dates in the program to my client. He also wants to see actual start/finish dates. Is it possible to do this?
-
An Admin deleted bucket
Saw a few threads regarding years of no action by SS to give the Admin the ability to restore deleted rows. My suggestion, why not allow users with edit rights to delete rows, but not allow them to see the deleted items. This is where the admin will go when the team screams that someone deleted a row or rows. SharePoint…
-
Conditional format using two columns
Hi, I have two columns Planned start and Actual start. I can't seem to set a conditional formatting rule when Planned start is not equal to Actual start. Please assist. Y
-
Image-Hyperlink
Wondering if there is a way to make an image as a hyperlink (Click on image). I have tested the option of adding image in cell, and also just add hyperlink with text, but I do not see way to actual make the image as a hyperlink. Thanks for any input.
-
Web Forms
The only way that I know to add an attachment accessible to the user is to create a link. (I'm not referring to the user uploading a document to the web form.) Is there another option?