-
How to enter specific text if the cell contains a partial match?
My If statement: =IF(OR([Task Name]@row = "Discovery", [Task Name]@row = "Analysis", [Task Name]@row = "Build", [Task Name]@row = "Test", [Task Name]@row = "Deploy", [Task Name]@row = "Design"), "PMO", IF(OR([Task Name]@row = "PER", [Task Name]@row = "PRT", [Task Name]@row = "CK1 RTS", [Task Name]@row = "CK2 RTB", [Task…
-
How to Consolidate Entries from Multiple Forms
I've seen this question asked before, and the same answer is always given, "use an update request." Is there a way to consolidate information, because I don't think update requests are the best solution for our process. I have multiple forms with different types of information being entered at different times by different…
-
Project Schedule/Milestone Tracking Solutions
Hi Everyone! Does anyone have a project schedule/milestone tracking solution to share? I'm trying to create a company wide solution to input/track schedules for multiple projects, multiple milestones within each project, and provide executive level visibility of the status of each project. Any good ideas would be…
-
All Dates populate based off one date
Hello, I am trying to create a sheet where I can put in one date in the Target Start Date column then all other dates populate from that date based off the duration it takes to do all the task. Is this possible?
-
Is it best to link only one predecessor to each task or is it ok to have multiple?
I am working on a construction schedule and wondering what the best practice is for attaching predecessors. I have noticed my Gantt chart is currently a bit all over the place and I am thinking it is because I have too many predecessors for each task. Do more experienced Smartsheet users recommend only having one…
-
Excited to Implement Work Apps
I’ve learned a lot at the conference, but I’m most excited to implement Work Apps with the teams I work with. A one stop shop of all the necessary information will help improve their efficiency.
-
Very ENGAGING at #Engage2022
Having so much fun and learning all the things at Engage 2022 in Seattle!
-
Help Searching Mutiple Job#
I want to be able to insert in my table the information: PO,Project Description,Customer,Payment Teams,Business Unit,Submitter,Notes from anothe sheet that contains the Job information. From the Job# column, I've done it before with an index match but only when is one project. I want to be able to do it for multiple Job…
-
Total Site % Complete + health
I need the total site % Complete Each milestone has % complete for the site project What is the sample formula to calculate each milestone % complete columns to give the site Total % complete? Let’s say, Milestone ABCDEF etc I just want to SUM all the milestone % complete to give me the total project % complete Then the…
-
TOTAL% COLUMN