Correcting chart spacing
I am creating a chart on a dash board using a sheet summary report pulling data from 2 sheets. I am having difficulty arranging the columns as desired no matter how I adjust the widget tools or the columns in the report Specifically, One column that is pulling data from sheet "A" is on the left and the other 3 columns…
-
How to query data from one sheet to another?
I have a sheet which is essential reference data. I then have another sheet which will be used to actually do management with, but it needs to "pull" data from the reference sheet. VLOOKUP is only returning one data set. How do I use Smartsheet to query the reference sheet and return a list of rows which match a specific…
-
Can we create a report to find which sheets have proofs attached?
We have multiple project sheets and our team uses proofs within those sheets. I want to create a report to find out which sheets have proofs attached to them. Is it possible? If not report, is there any way using formulae that we can find out if the sheet has proof? For example, if the sheet has a proof attached, a…
-
Report Grouping Work Around
I have a list of SOPs and their supporting documents (Forms, Logs etc). As you can see in the Excel example, we have the SOPs in Green and the supported docs below. Some, like the SOP Training/Retraining Record, are used for multiple SOPs. I tried: Using Gantt functions, added a Predecessor Column but I couldn't run a…
-
Report Row Sorting
I am trying to use reports to reduce the amount of columns and rows I need to handle via the API. Along with this, I would like to have the report also sort the rows, but it seems that when using the API make a Get Report request, the row numbers in the JSON response do not line up with the associated reports row numbers.…
-
Formula for 2 columns - checkbox and a date range
Hi there - newbie here. Looking for help with a formula. I am trying to drive a metric which shows the percentage of activities on 'THD Brands' in the past week. The 'THD Brand' column is a checkbox, so essentially I need to count anything that is ticked in this column, and also the 'Last met?' column has a date within the…
-
Logic Project Plan
Hi , Need a help on the project plan logic related to Sch Health. The logic i am using on the schedule Health is not showing me the correct result. As you can see Start date is 06/01 and End Date is 06/30 the % Complete is 50% ideally it should be green because it just a week and the % complete is 50% Can any one help on…
-
*NEW: Proofing using Reports
The new Proofing capability is something we would like to implement in our department, but we are having issues with accessing this in Reports. We see that Proofing can be done in the main smart sheet, but our Artists access new design requests via Reports so that they only see what tasks and designs are assigned to them.…
-
Do we have an update on Proofs being available in Reports?
Hello, My teams love having personalized reports but the function that we need the most is Proofing. Would there be an estimated time of when that the Proofing Function will be available in reports? Thank you, Johnathon S.
-
Filter reports - How to
I'm building a late task report across multiple workspaces/plans. The filter option is not available when viewing report results. Looking to be able to filter by "Status", "Owner", etc.