Discussion List
Change the owner of a workspace
Hi, It's possible to change the owner of Worksheet. But is it also possible to change the owner of a Workspace? kind regards, Wouter
Counter on Report
Is there a way to add a column to a report? I have multiple SmartSheets managing Test Scripts in multiple functional groups and I want to create a bug report for the developer that searches them all and only shows them the "Fails", but I would like the failures to get a unique identifier. Is it possible to add a column…
Merging cells
Hi! Is there a way of merging cells across one row? Thanks.
Time Management in Start and End Date
Hi I saw some items where people wanted to manage time in Start and End Date. This is a feature that interets me for laptop usage. Can you tell me please if it is planned en the smatsheet roadmap ? Thank you for answer
My tabs have disappeared
Please help restore. A year of team efforts and everyone's gone.
Baseline
How can I establish a baseline in smartsheet? I am using smartsheet for construction scheduling. Like many industries there are delays. However, in construction delays come with a cost, a dollar amount that needs to be paid when projects go over their time line. I establish my schedule when I start a project. Throuhgout…
Smartsheet merge in Google Docs: list sorting and/or filtering
Smartsheet Merge in Google Docs is a very useful add-on that I use very often. I can adjust a lot of things (creating/sharing/uploading GDocs and PDFs, as well as sending them to specific clients via email - just awesome). My only pain is to find the specific rows in a huge list of clients in the “Select Smartsheet Data”…
Start-to-Finish Predecessors Doesn't Work as Expected with Multiple Predecessors
Hi there, I'm running into a roadblock I'm hoping someone could help with. I'm planning my schedule backwards from an end date, and using Start-to-Finish Predecessors as recommended in this article (http://help.smartsheet.com/customer/portal/articles/765727). Here's the problem: I have a task (let's call it Task 1) that…
Browser showing Smartsheet url with a red bar through it?
Hi Community One of our clients who uses a laptop within a large org, all operating the same AntiVirus and google docs for work environment but no one else has experienced this... see attached graphic. Any ideas what this is or how to resolve it?
reporting tools
Is there any reporting tool available other than the reports feature in smartsheet? I'm looking to build a custom non-tabular report showing different cells of a single row.