Hi there,
I'm running into a roadblock I'm hoping someone could help with.
I'm planning my schedule backwards from an end date, and using Start-to-Finish Predecessors as recommended in this article (http://help.smartsheet.com/customer/portal/articles/765727).
Here's the problem: I have a task (let's call it Task 1) that must be finished before two different tasks can start (let's call them Task 2 and 3). But, when I use the Start-to-Finish Predecessor (Task 1, shows 2SF and 3SF as Predecessors) it allows Task 2 to start before Task 1 finishes. However if I delete Task 3 as a SF Predecessorfor Task 1, it correctly aligns Task 2 to start after Task 1.
Any help is much appreciated.