Suggestions - Customize toolbar
Hi, I would like to suggest the ability to customize the toolbar. Reordering buttons, removing functions, adding functions. I personally would like to pull the Refresh option out of the menu and place it on the toolbar as a large button. Thanks, E
-
When a task is complete ahead of schedule the dependent tasks start date is not brought forward
Hello i have tasks a,b,c - all tasks are 2 days in duration task 'b' is dependent on 'a', and task 'c' id dependent on 'b' task 'a' was scheduled to start on 1/1/16, but it was started earlier and so it was marked complete on 31/12 how do i set it up so that task 'b' now slides along to 31/12 showing it is available toโฆ
-
Alerts & Notifications
Hello all, I'm trying to build a sheet that notifies the right person when certain new records are entered (e.g. alert Person X when a new record is entered that has a certain column equal to ABC). In reading through some of the posts, I understand that "conditional alerts" aren't developed yet so I'm looking for otherโฆ
-
Car Rental Calendar using Gant
Hello Everyone; My wife and I own a car rental company in beautiful St. John in the U.S. Virgin Islands. The previous owners have always used a paper calendar reservation system which essentially has all 70 cars on the right hand side of the board and three months of columns to the left. Is there a way to ceate a gantโฆ
-
Work Column
Hello, In MS Project there's a column called "Work". that if I write for example for an X task, 6 days in the work column, and assign 2 persons on this task >> the duration will be 3 days. How can I have it in your gantt? G.
-
SIGHTS report formatting
I'd like to reformat a report on a SIGHT board, i.e. make text smaller to avoid an expanded column in the view. Is there a way to lock the column widths? The default is too big and the imported report won't resize. thanks!ย
-
Conditional Formatting - Target Dates vs Actual Dates
Hey guys & gals Basically I'm trying to get my actual task finish date to highlight green or red if it hits or doesn't hit the target date. I know I need a checkbox column to do this. I've added one with the following formula =IF(Finish2 > Baseline2, 1, 1) Finish2 = the first cell with the actual finish date Baseline2 =โฆ
-
Pre existing excel spreadsheet into smartsheet
Hello I have 2 existing excel spreadsheets that I want to put into smartsheet approach, so everyone can add/wotk on it as needed. What is the best way to do this? Thank you! :)
-
Duration in months
How can I set the Duration column to be in months, instead of days, weeks...? thanks Gally
-
Excel sync
Hi there, does anyone know if it is possible to synchronize excel data with smartsheet. My problem: our erp system can export lot's of project data to excel. So it would be nice to sync a main smartsheet with the erp data and have nice things like sights and more ... thks Peter