Mutliple dates displayed as milestones in a Gannt report
Hi
I have a portfolio sheet of project titles in rows that lists their Stage Gate dates (SG1-6) in columns. I want to create a report that shows those dates as milestones in a Gannt - each row (project) would essentially display 6 milestones. Is there any way to do that?
Best Answer
-
Unfortunately not - company is a new adopter of Smartsheet and has not activated Control Centre yet
Answers
-
Hi @RayB ,
Gantt view will allow up to 2 dates per row, ie: Start & Finish date, and they wouldn't show as milestones but instead a colored bar. The actual Milestone markers need a 0 day duration. In order to do what you are wanting each SG would need it's own row.
Is this portfolio sheet a summary sheet made in Control Center? If so, can you pull these dates in from project sheets using a report?
-
Unfortunately not - company is a new adopter of Smartsheet and has not activated Control Centre yet
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 62 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives