Mutliple dates displayed as milestones in a Gannt report

Hi

I have a portfolio sheet of project titles in rows that lists their Stage Gate dates (SG1-6) in columns. I want to create a report that shows those dates as milestones in a Gannt - each row (project) would essentially display 6 milestones. Is there any way to do that?

Best Answer

Answers

  • JCluff
    JCluff ✭✭✭✭

    Hi @RayB ,

    Gantt view will allow up to 2 dates per row, ie: Start & Finish date, and they wouldn't show as milestones but instead a colored bar. The actual Milestone markers need a 0 day duration. In order to do what you are wanting each SG would need it's own row.

    Is this portfolio sheet a summary sheet made in Control Center? If so, can you pull these dates in from project sheets using a report?

  • RayB
    RayB ✭✭
    Answer ✓

    Unfortunately not - company is a new adopter of Smartsheet and has not activated Control Centre yet