Hi
I have a portfolio sheet of project titles in rows that lists their Stage Gate dates (SG1-6) in columns. I want to create a report that shows those dates as milestones in a Gannt - each row (project) would essentially display 6 milestones. Is there any way to do that?
Best Answer
-
Unfortunately not - company is a new adopter of Smartsheet and has not activated Control Centre yet
Answers
-
Hi @RayB ,
Gantt view will allow up to 2 dates per row, ie: Start & Finish date, and they wouldn't show as milestones but instead a colored bar. The actual Milestone markers need a 0 day duration. In order to do what you are wanting each SG would need it's own row.
Is this portfolio sheet a summary sheet made in Control Center? If so, can you pull these dates in from project sheets using a report?
-
Unfortunately not - company is a new adopter of Smartsheet and has not activated Control Centre yet
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 142 Industry Talk
- 473 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives