I want to develop a template sheet that I can use to easily schedule out 30 to 60 different 30 min subtasks evenly over 200 specific available work days each year. I started out trying to set up a gantt view row with "200d" working day duration then removing sat/sun, and inputting 62 other Non-working days in gantt view project setting in order to show the time line of actual working days available in the year but it doesn't seem to want to register the non working days so the time line is just 200d long ... so that's not working.
I was thinking I could divide the 200 days allotted for the project by the number of sub-tasks and then make that the duration of my sub tasks and set that as my base line and then set all my task rows up as finish-to-start predecessors. this way I could tell where I'm at by how my actual dates for sub-task completion compare with the baseline projections.
ether way i think i would need that "non-working" days project setting to work.
if there's an easier way... maybe I just pre fill a template with 30-60 rows with projected dates and count them down... id be very interested if anyone has tackled similar issues