View multiple (start and end) dates in Gantt view at the same time
Hello everyone, so I am working on a transformation project that has many iterations/phases with a start date and an end date, so I have 5 phases with a start date and an end date, is it possible to view those 5 phases at the same time in Gantt view, like being separated and not as a same block ? Which means there are 10 colums with different dates for the same row and I wan to view the different milestones for those sames rows. I don't think it's possible but I want to be sure. Or maybe do I have to create all these phase as statutes and only have 2 columns of dates.
Thank you for your answers.
Best Answer
-
Gantt can only display a single set of date columns unless you are using the Baseline feature. In that case it can only show two date sets (baseline vs actual).
Answers
-
Gantt can only display a single set of date columns unless you are using the Baseline feature. In that case it can only show two date sets (baseline vs actual).
-
Thank you so much you are a lifesaver and you made not waist my time ! Bless you !
-