Hours/Minutes in Project Sheet

Options
L_123
L_123 âś­âś­âś­âś­âś­âś­

I want to be able to make standardized work documents for changeovers/process information. I can't do that in smartsheet due to the lack of hours/minutes in the project sheets (I want to have the gantt chart to the right)

Of course I could do something like

  1. scale it with the days with 1 day = 1 hr and just ignore the wrong headers
  2. use conditional formatting with a helper column to jerry rig something together
  3. post a chart to a dashboard and use a report to have the data next to it

but it would be nice if I could just say a task is 5 hours right in the sheet and see it reflected with the correct formatting like I can with the days, and build task hierarchies/see the critical path