Resource Management: Handling of Milestones
Gabi
✭✭✭
I usually assign a resource to a Milestone (task with 0 duration), but now in RM for Smartsheet, if I do so, the resource is considered as 100% booked.
Form my point of view, if I do that, that should not be the case as the duration is 0. Or am I wrong?
Tags:
Answers
-
Hi @Gabi
If you don't want the milestone to impact a team members utilization, I'd recommend setting the Allocation % for the milestone to 0% 🙂
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 430 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives