Formulas and Functions

Formulas and Functions

Ask for help with your formula and find examples of how others use formulas and functions to solve a similar problem.

Is it possible to hide dates in a project plan and display week 1, week 2, etc.?

✭✭
edited 09/12/23 in Formulas and Functions

I'm setting up a project where the start date is still to be determined.

I have been asked to provide a column that has the week a certain activity needs to occur in. For example, instead of kicking off the project on 25/09/2023 the Grid View of the project plan should have a column in it that shows the project kicking off in Week 1.

Later activities should show how many weeks it's been since the start date. For example, if it's a 15 week project, the go-live would be in week 15.

Is there a way to do this through formulas?

Thanks in advance!

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!

Trending in Formulas and Functions