How to create a task that starts when the project starts and ends when the project ends?
kibister
✭✭
I have three oversight tasks for PM, Executive Sponsor, and Technical Director. I want them to start when the project starts, and end when the project ends. In MS project this was done by "anchoring," where I would copy and past the start date in the column, and then if the start date that was originally copied was changed, then the date that was pasted would change too. Is there a way to do this in smartsheets?
Tags:
Answers
-
Hi @kibister,
You can do this using dependencies and predecessors. This article should help:
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Melissa Yamada
melissa@insightfulsheets.com
Data made simple, spreadsheets reimagined
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 494 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives