Resource Management | Confirmed vs Unconfirmed Hours
Hello, Community! In RM, I've noticed that incurred hours includes confirmed and unconfirmed hours in RM. This is where I've directed PMs to obtain the actuals and total number of hours for the project. There is an 'Account Setting' that has 'Incurred Hours and Amounts'. It is currently set at 'Confirmed hours and unconfirmed past scheduled hours' - there is an option to have 'Confirmed hours only'. If we were to make that change would that impact the 'Project Actuals To Date'?
Answers
-
Are your individual contributors logging their time in Resource Management? If no, I believe you would see "Project Actuals To Date" plummet.
This resource may be more helpful...https://help.smartsheet.com/learning-track/resource-management-system-administration/time-tracking-settings Section 5
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives