When a project and tasks are set up with dependencies and durations, the project manager should be able to drive all task dates based on the project end date, not just the start date.
Often mid project the delivery date needs to be changed. With Smartsheet, a project manager needs to adjust the duration of all tasks manually until the the delivery date meets the new date set by the business.
In MS Project and other PM software, it is possible to manually change the delivery date, and see the impact on all predecessor tasks because of the durations set. It's much quicker, and more informative because it doesn't compromise all tasks durations that have likely been agreed upon by the owner of that task.
A shift in end date will usually result in current and upcoming tasks becoming overdue, and it gives the PM the opportunity report impact of an adjusted delivery date back to the business and provides the opportunity to assess tasks that can accomodate a shorter duration in conjunction with the owner of those effected tasks.
Thank you!
You've probably seen the but it may help?
https://community.smartsheet.com/discussion/77229/using-successor-links-instead-of-predecessor-links
The 'using successor links' option doesn't work for the functionality needed. Definitely an upvote for Nicole's recommendation.
I have to say, perhaps 'project management' and what I would expect of it differ from most other people's interpretation of the term, but I am a bit surprised that you can have a project management system that doesn't have the inherent ability to deal with the idea that a project has to be completed by a set deadline.
Update on this implementation please.
This is scheduling 101. There's no excuse for not having this basic scheduling functionality.